Challenge

The Environmental Regulator halted all production at the client’s facility in Shashi due to the performance of the Wastewater Treatment Plant (WTP). This shutdown resulted in significant production losses over the month of lost production.

The WTP had a series of physical, processing and management issues that were preventing it from performing to the regulator’s requirements.

Solution

SLR’s Industrial Wastewater experts within their Process Engineering Group provided on-site technical assistance, so the WTP could meet the regulatory requirements. After three weeks production had restarted, and after three months and further support, the WTP was operating in an ideal fashion.

Impact

By promptly aiding the facility to restart production, SLR staff directly prevented further significant commercial losses from the client.


Related projects

See all projects
  • Project

    UK

    Confidential

    Manufacturing & Industry

    Environmental strategy: combined energy, carbon, water and waste savings


    Read more
  • Project

    Hull and Nottingham, UK

    Pharmaceutical production sites

    Manufacturing & Industry

    Reducing API in wastewater stream


    Read more
  • Project

    Kauri, Northland, New Zealand

    Croft Poles & Timber

    Manufacturing & Industry

    Sawmill and timber processing facility - planning and technical assessments


    Read more